Google buys Putnam County land, with major construction details still pending
West Virginia announced approval for an early-stage data center project in March. The release includes utility cost commitments but no site hiring count.
What is being built. Who is doing the work. What it means for your crew.
West Virginia announced approval for an early-stage data center project in March. The release includes utility cost commitments but no site hiring count.
Missouri describes a $1.4 billion campus and hundreds of expected construction jobs, without a trade-package schedule.
Meta's Lebanon campus has a 4,000-worker peak forecast. The work reaches beyond the buildings into power, water, local infrastructure and the labor market.
The Mississippi expansion comes with grid and cooling plans. More than 75 state businesses are already involved in Madison County construction and operations.
The Pennsylvania project page lists 20 planned data centers, while commissioning dates remain unsettled.
The Nebraska opening marks a change in project stage. Google’s statewide investment figure covers three communities, not Lincoln alone.
Meta reported 2,300 workers onsite in July. The financing deal covers buildings, power, cooling and connectivity, with capacity expected online in 2028.
July work in Hebron covered grading, ponds and fencing. The owner expected substation work to begin before vertical construction.
The Missouri campus has potential capacity of 1.2 GW. Its owner distinguishes an initial utility connection from later power expansion.