DOE offers up to $2.8 billion for a Wyoming line linking the eastern and western grids

Grid United's Wyoming Intertie would run about 106 miles and carry up to 1,800 MW between the two grids. DOE's November 17 commitment is conditional, and the route still needs county, state and federal approval.

Carbon, Albany and Platte counties, Wyoming · Announced

Reported milestone:

The Department of Energy has offered up to $2.8 billion in financing for the Wyoming Intertie, a transmission line that would connect the country's eastern and western power grids. DOE announced the conditional loan commitment on November 17. The developer is Grid United.

What would the line do?

The U.S. grid is split into the Eastern Interconnection, the Western Interconnection and Texas, with few links between them. DOE says the Wyoming Intertie would add about 1.8 gigawatts of transfer capacity and double what can move today between the Southwest Power Pool and the western grid region.

According to the project's own site, the line would run about 106 miles across Carbon, Albany and Platte counties and connect substations near Medicine Bow and Wheatland. It would carry power in both directions from any type of generation. Grid United describes it as an approximately $3 billion investment in Wyoming.

DOE estimates up to $39 billion in electricity cost savings across 17 states. That is an agency projection over the life of the project, not a measured result.

How close is it to construction?

Not close yet. DOE's commitment is conditional: the project must meet technical, legal, environmental and financial conditions before DOE signs final financing documents and funds the loan.

The route is also still a proposal. Grid United says it is working with landowners and Tribal Nations on the route, which stays proposed until county, state and federal regulators approve it. Construction starts only after land rights and approvals are secured. The developer says the line could be running in the early 2030s.

What does it mean for line and substation work?

DOE says the project will create hundreds of construction jobs and long-term operations jobs, without a firmer number. Neither DOE nor Grid United names contractors.

BEJ's reading is that a project like this means high-voltage line construction plus major substation work at each end, the kind of scope that draws line crews and substation electricians from across the region. The dates to watch are the county permit decisions, the federal environmental review and the loan closing, since each one has to come before crews mobilize.