Google plans its first Wyoming data center with 702 MW of fuel-cell power

Google calls the Laramie County campus a long-term $17 billion investment. AEP is contracted to build a 702 MW natural-gas fuel-cell plant with carbon capture. Google has not given a construction schedule.

Laramie County, Wyoming · Announced

Reported milestone:

Google announced its first Wyoming data center on November 5. In a post by Steve Walter, its vice president of global infrastructure and energy, Google called the Laramie County project a long-term $17 billion investment. Its partners are Tallgrass Energy, Black Hills Energy, American Electric Power (AEP) and Related Digital.

How will the campus be powered?

The largest piece is a 702 MW fuel-cell plant contracted with AEP. The fuel cells, made by Bloom Energy, turn natural gas into electricity. A carbon capture system would send most of the plant's carbon emissions to Tallgrass's nearby Eastern Wyoming Sequestration Hub. Google calls it the largest planned development of its kind.

Google will also buy power from gas generators run by Tallgrass and Black Hills Energy. It is studying whether Tallgrass's combined-cycle turbines could be fitted with carbon capture. The data center itself will be air-cooled to limit water use.

The 702 MW is the fuel-cell plant's capacity. It is not the data center's load, which Google does not state.

When will it be built?

Google does not give a construction start, a completion date or a building count, and it names no general or electrical contractor. The post does not mention state permits or utility approvals. BEJ has not found a public approval record for the AEP fuel-cell plant, so this story treats both the campus and the power plant as announced plans.

What does this mean for electrical work?

Google's post gives no construction job count. It says Google will fund skilled-trades training across Wyoming and that the project should bring hundreds of millions of dollars in property taxes to Laramie County and School District 1.

For electricians, the project combines a large data center campus with a new fuel-cell power plant, gas generation and carbon capture, each with its own electrical work. Cheyenne already has data center growth: BEJ has covered Microsoft's 3,200-acre expansion planning there. The schedule for the fuel-cell plant and the campus will decide when that work actually reaches the field.