NRC approves construction permit for Dow's four-reactor Long Mott plant in Texas
The November 9 permit covers four X-energy Xe-100 reactors at Dow's Seadrift site. It does not allow operation, and Dow has not made its investment decision; a preliminary decision is expected in 2027.
The Nuclear Regulatory Commission approved a construction permit on November 9 for the Long Mott Generating Station, a proposed nuclear plant at Dow's Seadrift Operations site in Texas. In their joint announcement, X-energy and Dow said the permit went to Long Mott Energy, a Dow subsidiary.
What would be built?
The plant would use four of X-energy's Xe-100 reactors. Each is designed to produce 80 megawatts of electricity or 200 megawatts of heat. DOE's Office of Nuclear Energy says the four together could supply up to 320 megawatts of electricity along with high-temperature steam for Dow's manufacturing operations. The companies say the plant would replace energy and steam equipment nearing the end of its life.
It is the first advanced nuclear plant approved for construction at a U.S. industrial site. The companies call it the first NRC construction permit for a high-temperature gas-cooled reactor in nearly 60 years. The project is part of DOE's Advanced Reactor Demonstration Program.
Does the permit mean construction starts now?
No. The permit is federal approval to build the plant to the approved design. It does not authorize operation: Dow would need a separate NRC operating license before loading fuel.
Dow has not decided to build. The companies say Dow is expected to consider a preliminary investment decision in 2027, and full-scale nuclear construction would begin only after a final investment decision by Dow's board. For now, the work is finishing the reactor design, lining up long-lead components and preparing the operating license application. The target for first power is the early 2030s.
What does it mean for electrical work?
Neither the companies nor DOE give a construction job count. BEJ's reading is that if Dow approves the project, building four reactors inside an operating chemical plant would mean nuclear-grade electrical, instrumentation and controls work next to an industrial site that keeps running. The date to watch is Dow's 2027 preliminary decision. Until a final investment decision, the project's near-term work is engineering and supply chain, not field construction.